- JnNURM is a Government of India (GoI) scheme to
revitalize Urban Infrastructure and Governance in 65 Mission cities across
the Country.
- The Mission comprises two sub-missions, viz.,
the Urban Infrastructure & Governance (UIG) and the Basic Services to
the Urban Poor (BSUP), which are being implemented in Bangalore and Mysore
of Karnataka.
- Mission period is from 2005-06 to 2014-15
1. Urban Infrastructure and Governance (UIG)
·
Under UIG
Sub-Mission, 49 projects were sanctioned at an estimated cost of Rs. 3765.84
crore of which 39 projects estimated Rs. 2887.19 crore were for Bangalore and
10 projects estimated Rs. 878.65 crore for Mysore city.
·
32 projects have
been completed as on 31st March, 2016.
Achievements of the three
years (Apr 13-March 16):
Physical Progress:
During the period, 7 projects have been completed as
below:
·
Development of Transport Infrastructure Facilities
of Mysore City.
·
Intelligent Transport System and Innovative
Environment Project for Mysore City.
·
Underground Drainage System in Yelahanka Town
·
Water Management through Surface and Rainwater
Harvesting at Sri Chamarajendra Zoological Gardens
·
Upgradation of 2 Lane Outer Ring Road to 6 Lane of
Mysore (Bangalore to Nanjangud Road)
·
Underground Drainage System and Road Restoration
in R.R.Nagar
·
Underground Drainage System in Kengeri Town
Financial
Progress:
·
During the period, Rs. 274.19 crore (Central and
State share) has been released for 49 projects under this Sub-Mission. Of
which, Rs. 906.28 crore has been spent including ULB share.
2. Basic Services to the Urban Poor (BSUP)
·
Under BSUP
Sub-Mission, 18 projects were sanctioned at a cost of Rs. 837.79 crore of which 14 projects at Rs. 578.95
crore were for Bangalore and 4 projects estimated at Rs. 258.84 crore were for
Mysore city.
·
Total
27925 dwelling units, with all essential services, in 158 slums of Bangalore
and Mysore together, have been approved so far.
·
26707
DUs have been completed and 948 DUs are under construction. Totally, 6 projects
have been completed. The financial progress is Rs. 769.53 crore as on March, 2016.
Achievements in 3 Years (Apr 13-March, 2016):
Physical
progress:
During
the period, out of total 18 projects, 6254 DUs and 4 projects have been
completed as below:
·
Nagareshwara Nagenahalli slum area for the construction
of 208 DUs.
·
Kanteeravanagara slum area for the construction of
487DUs.
·
Roshan Nagara slum area for the construction of 320 DUs.
·
Veerabadranagar
slum area for the construction of 256 DUs.
Financial Progress:
·
During this period, Rs. 133.68 crore has been released (Central and State share) and
Rs. 211.63 crore has been spent,
including beneficiaries share.
Reforms:
·
JNNURM mandates
implementation of Reforms for which the State has signed a MoA with Govt. of
India.
·
Out of 23 State and City
level reforms, all the 23 reforms have already been implemented.
·
11, out of 12 Urban
Transportation related Reforms have been implemented.
Achievements
in the three years:
· 1 Reform, namely, Earmarking
of at least 20-25 percent of Developed Land in all Housing Projects (both
Public and Private Agencies) for EWS/LIG Category with System of Cross
Subsidization has been implemented during this period.
·
Calibration
of Reforms: Karnataka Scored
(Calibrated) 95.4% Marks for implementation of Reforms mandated under JnNURM
and stands 2nd rank in the Country.
·
The State has been
recognised as the best performance State in implementation of JnNURM (BSUP)
schemes.
JnNURM - Transition
Phase (TP):
1.
Urban Infrastructure and Governance (UIG): 7 projects
amounting to Rs 418.14 crore have been approved till date. Of this, Central
Government share is Rs. 272.63 crore and State Government share is Rs. 48.69
crore, against which the Government of India has already released Rs.68.16
crore and Government of Karnataka has release
its share of Rs 12.17. crore.
· Additional Central Assistance (ACA) has been revised
from Rs.272.63 crore to Rs.188.42 crore for UIG-TP projects by GoI and the
grants will be released under AMRUT.
Achievements in 3 Years
Financial
Progress: During the
period, Rs. 6.32 crore has been spent including ULB share.
2. Urban Transport: For Bangalore and Mysore 8 Projects amounting to Rs
298.50 crore have been approved. Of this, Central Government share is Rs. 108.03 crore and State
Government share is Rs. 43.20 crore, against which the Government of India has already released Rs.54.00
crore and Government of Karnataka has release its share of Rs 21.60. crore.
· Total No. of Buses sanctioned has been revised from 926
to 593. ACA for UT projects has been revised from 108.03 to 98.54 crore
committed by GoI under AMRUT.
Achievements in 3 Years
Physical progress:
·
During the period, out of
total 8 projects, 1 project, namely, Construction
of Bus Depot at M.S. Palya has been completed.
Financial
Progress:
During the period, Rs. 42.25 crore has been spent including ULB share.